Lima-Lima City engineer Kirk Niemeyer has announced a schedule for upcoming street resurfacing projects.

• East McKibben Street, between North Jackson Street and the dead end, Milling begins on Monday. Pavement begins on Thursday.

• East Pearl Street from North Main Street to the dead end. The milling board starts on Monday. Pavement begins on Friday.

• Between Liberty Street, East Pearl Street and East McKibben Street. The milling board starts on Tuesday. Pavement begins on Friday.

• South Jackson Street between East Kibby Street and East Eureka Street. The milling board starts on Tuesday. Pavement will begin on October 18th.

• East Third Street from St. John’s Avenue to South Sugar Street. The milling board starts on Wednesday. Pavement will begin on October 19th.

• East Kibby Street between South Main Street and South Pine Street. The milling board starts on Thursday. Pavement will begin on October 20th.

• From North Baxter Street, West North Street to Tremont Avenue. The milling board starts on Friday. Pavement will begin on October 21st.

• West O’Connor Avenue, west of the dead end to Brendonwood Drive. The milling board will start on October 18th. Pavement will begin on October 22nd.

• Lunyan Avenue between North Wald and North Metcalf Streets. The milling board will start on October 20th. Pavement will begin on October 25th.

• Brice Avenue between North Rosedale Avenue and North Jameson Avenue. The milling board will start on October 20th. Pavement will begin on October 25th.

• Westmarket Street between Woodlawn Avenue and North Charles Street. The milling board will start on October 21st. Pavement will begin on October 26th.

• West Wayne Street between North Cable Road and North Glendale Avenue. The milling board will start on October 22nd. Pavement will begin on October 27th.

• Oakland Parkway between North Cable Road and Westwood Drive. The milling board will start on October 22nd. Pavement will begin on October 27th.

• Central service parking lot. Milling begins on October 23rd. Pavement will begin on October 28th.

According to Niemeyer, the city’s contractor, Sherry, will not post parking signs before pavement and milling operations. The dates are approximate and subject to change due to weather conditions.